CIP# Project Description Cost Start End Info
N/A Freeway On/Off Ramp Pavement Rehabilitation (Central Ave, Wilmington Ave, Santa Fe, Alondra Blvd) The project will address potholes and street issues at major on and off ramp locations TBD 05/04/19 TBD Details
Last Update 05/09/2019
N/A Compton Blvd and Wilmington Ave Over Compton Creek Bridge Replacement Projects Replace the bridges on Compton Blvd and Wilmington Ave over the Compton Creek and considering addition of bike facilities. TBD 12/31/2023 12/31/2026 Details
Last Update 05/02/2019
18-02 Wilmington Ave Safe Streets Pedestrian / Bicycle Improvement Project (Design Phase) - Rosecrans Ave to Greenleaf Blvd The project will address the need to provide safe crossings for students and residents at each intersection and improvements to access the Compton Creek Bike Path. $447,043 02/12/19 estimated
12/31/2022
Details
Last Update 04/23/20
19
 18-03  Compton Blvd Street (Design Services)  Provide full width roadway paving, add ADA ramps, raised median island, class ii bikeway, high visibility crosswalks, and LED lighting.  $1,467,812.01  12/6/18  12/31/2022  Details
Last Update 04/23/20
19
N/A
Completed
Citywide Pothole Repair Project (Phase 1) Providing approximately 5,000 square yards of pothole preparation work/materials and 1,100 tons of asphalt installation work along major streets. $640,000 12/17/18 TBD

Details (Citywide Pothole Repair Project (Phase 1)

18-01 Annual Street Rehabilitation -2A  Full reconstruction of the streets including specified sidewalks, curb and gutters, cross gutters, driveway approaches, curb ramps, signing, striping, speed hump and traffic loops on Alondra Blvd, Bullis Rd, Parmelee, and Stockwell/135th St. $6,465,000 12/15/21  11/01/22 Details
 18-01  Annual Street Rehabilitation -2B  Full reconstruction of the streets including specified sidewalks, curb and gutters, cross gutters, driveway approaches, curb ramps, signing, striping, speed hump and traffic loops on Slater Ave, Compton Ave, Rosecrans Ave, and Santa Fe Ave.  $6,840,972  11/1/2022  7/31/2023  Details
 18-01  Annual Street Rehabilitation -2C  Full reconstruction of the streets including specified sidewalks, curb and gutters, cross gutters, driveway approaches, curb ramps, signing, striping, speed hump and traffic loops on Alameda St., Walnut St., Walnut Parkway, and Walnut Park Drive.  $7,177,270  11/1/2023  4/31/2024  Details
 18-01  Annual Street Rehabilitation -2D  Full reconstruction of the streets including specified sidewalks, curb and gutters, cross gutters, driveway approaches, curb ramps, signing, striping, speed hump and traffic loops on Bradfield Ave. and Greenleaf Blvd.  $3,024,120  8/1/2024  2/28/2025  Details
18-01 Annual Residential Street Rehabilitation Project (Design Phase) Review existing pavement conditions; identify all distressed pavement areas, curb-gutter, and sidewalks; make recommendations as to the extent and type of rehabilitation needed. $518,000 11/14/18 TBD Details
Last Update 04/23/2019
N/A
Completed
Metro Rapid Bus Stations Installation of Metro Rapid bus station amenities along Atlantic Blvd at three locations with the City limits. $9,000 06/07/17 01/11/19 Details (Metro Rapid Bus Stations)
 N/A Completed  Citywide Pothole Repair Project (Phase 1)  Providing approximately 5,000 square yards of pothole preparation work/materials and 1,100 tons of asphalt installation work along major streets.  $640,000  12/17/2018  TBD  Details (Citywide Pothole Repair Project (Phase 1)
17-05
Completed
Compton Blvd Resurfacing Project (Phase 1) Installed hot mix overlay; traffic loops; signs/stripping; traffic pavement markers and curb painting $553,011 11/13/17 12/18/17 N/A
17-01
Completed
Central Blvd Resurfacing Project (Phase 2) - 131st to Compton Blvd Repair, replace, and slurry sealed existing pavement. Install ADA compliant curb ramps, gutter, sidewalk improvements. $2,137,386 04/26/18 12/18/18 N/A
15-03
Completed
Compton Blvd Resurfacing Project (Phase 1) - Compton Blvd to Greenleaf Blvd Repair, replace, and slurry sealed existing pavement. Install ADA compliant curb ramps, gutter, sidewalk improvements. $1,688,160 06/06/16 10/18/16 N/A
15-01
Completed
Safe Streets Pedestrian / Bicycle Improvement Project (Phase 1) Wilmington Ave Improve pedestrian and bicycle safety adjacent to Wilmington Ave transportation corridor. Install bike lanes. $1,396,430 12/16/16 04/11/17 Details (CIP 15-01)
14-01
Completed
Residential Street Resurfacing Replacement of sidewalks, curbs, gutters, and roadway pavement treatments $2,032,008 10/07/14 01/19/16 N/A
13-02
Completed
Street Rehabilitation (Residential) Installed asphalt pavement; removing and replacing failed asphalt concrete area, installed ADA compliant ramps, street sign replacement $2,683,660 03/19/15 06/21/16 N/A
13-01 Street Rehabilitation Project Construction Phase Street pavement rehabilitation $2,400,000 02/25/19 estimated 08/07/19 Details
Last Update 06/13/2019
10-20
Completed
Sewer Replacement Project Wilmington and Alondra Area Improvement and restoration of about 7.5 miles of sewer. Improvements include sewer cleaning, CCTV inspections, point repairs of pipes, in-place sewer lining, and manhole rehabilitation. $2,393,555 05/12/16 09/05/17 N/A
10-18
Completed
Sewer Replacement Project Compton and Wilmington Area Construction of new VCP and Ductile Iron sewer mainlines; new sewer manholes; restoration and reconstruction of associated mainline construction and connections $5,915,292 07/20/16 07/18/17 N/A
10-10
Completed
Residential Street Overlay Removal and replacement of sidewalks and driveways; removal of existing curbs and gutters from eligible CDBG residential streets $1,516,496 06/02/10 01/18/11 N/A
09-12
Completed
ARRA Preventive Street Maintenance Grinding, overlay, and sidewalk repair at Poplar St, Laurel St, Acacia Ave, Tamarind Ave, Palmer St, and Alondra Blvd $530,500 04/12/10 06/02/10 N/A
09-10
Completed
ARRA Pavement Rehabilitation Grinding, overlay, and sidewalk repair for ADA compliance on Greenleaf Blvd and Santa Fe Ave $1,894,691 02/02/10 10/16/10 N/A
09-09
Completed
Williams Alley Paving Repave existing alley $298,887 03/03/14 07/22/14 N/A
09-06
Completed
Crane Ave Reconstruction Removal and replacement of sidewalks and driveways between Rosecrans and Compton Blvd. Replacement of road surface between Rosecrans to Alondra Blvd. $427,718 05/15/12 06/11/13 N/A